Elm Street Water Main Replacement Project

Overview

In Coordination with City of Bath Front/Elm St Streetscape Project:

  • Main Replacement & Relocation: 8” water main on Elm St from Front to Water Street.
    • Phase 1: Front Street Interconnection – Upgrade to new 12” main.Completed
    • Phase 2: Elm Street Main Installation – Replace and relocate 8” main.Completed
    • Phase 3: Elm/Water Street Tie-in & Hydrant Relocation – Move hydrant out of sidewalk.Completed
  • Restoration and Services:
    • Services: 1 dayCompleted
  • Pavement Restoration: Starting Friday June 14th – Completed

Phases:

  • Phase 1: 10-12 hours (Saturday June 1st – 10pm start)Completed
  • Phase 2: 4 Days (7am – 7pm)Completed
  • Phase 3: 1 Days (7am – 7pm)Completed
  • Service Installations: 1 Days (7am – 7pm)- Completed
  • Pavement Restoration: 2 Days (7am – 7pm)- Completed

Water Service Interruption – Completed: Thank you for your patience